Wall installations in Stockholm

We currently have two upcoming wall installation projects:

  • FSE401 – Approximately 100 walls for Skanska Sverige AB in Vinsta
  • FSE613 – Approximately 30 walls for Strabag Sverige AB in Akalla

We have installed precast wall elements for various contractors on the Förbifart Stockholm project. Wall installations have been carried out in several subprojects, including:

  • FSE209 Skärholmen – Over 5,800 walls (about 2,000 remaining) for Subterra Sverige AB
  • FSE105 Kungens Kurva – Approximately 600 walls for Skanska Sverige AB
  • FSE502 Hjulsta – Approximately 600 walls for NCC
  • FSE501 Hjulsta/Lunda – Approximately 100 walls for JV Veidekke/Implenia

Installation is carried out using our own personnel and equipment, including a Manitou 10130 with a hydraulic vacuum unit from AL-Lift.

Status

Completed

Category

Address

Stockholm

Completion

10/2023

Project manager

Veli Taatila